From Monday 4 May to Saturday 12 December, works to upgrade the Seveso railway junction will be carried out not only at night, when rail services are suspended, but also during daytime hours. As a result, on weekdays, excluding Saturdays, between 9 a.m. and 5 p.m., services on the S4 Camnago/Lentate – Milano Bovisa – Milano Cadorna line will be subject to changes.
DAYTIME WORKS – Extending working hours at Seveso is intended to meet the deadlines and targets set for the installation of railway tracks, electrification and signalling systems along the section between Seveso and Camnago. Work is progressing at a fast pace. Construction of the road underpass structure is currently underway. The final section of the underpass structure will be pushed into place during an extraordinary suspension of rail services, scheduled from the end of service on Friday 29 May until services resume on Wednesday 3 June. Work is also continuing on the construction of the retaining walls for the ramp on Via Sanzio, while excavation work is underway for the ramp on Via Zeuner to reach the required level for the foundation slab.
CHANGES TO RAIL SERVICES – On weekdays, excluding Saturdays, between 9 a.m. and 5 p.m., S4 services on the Camnago Lentate – Milano Bovisa – Milano Cadorna line will operate only between Palazzolo Milanese and Milano Cadorna. Passengers travelling between Palazzolo and Seveso can use S2 services on the Mariano Comense/Seveso – Milano Passante – Milano Rogoredo line. Replacement buses will operate between Seveso and Camnago.
The replacement bus service between Seveso and Camnago will be organised to ensure connections with S2 services at Seveso and with S11 trains on the Chiasso – Como – Milano – Rho line at Camnago Lentate.
Full details of the service changes are available on the Trenord website at trenord.it and via the Trenord app.
UPGRADING THE SEVESO RAILWAY JUNCTION – The works to upgrade the Seveso railway junction include, among other interventions, the renewal of railway systems and platforms, the doubling of the Seveso – Camnago Lentate and Seveso – Meda sections, the construction of a road underpass between Via Zeuner and Via Sanzio, and a pedestrian and cycle overpass on Via Manzoni. All information and updates are available at: https://www.ferrovienord.it/interventi-in-corso/
REPORTING CHANNEL AND INFORMATION POINT – For any questions, requests or clarifications regarding the works, railway infrastructure and FERROVIENORD stations, reports can be submitted using the methods published on the website at: https://www.ferrovienord.it/segnalazioni-e-reclami/.
An Information Point for construction works has also been opened at Milano Cadorna station. This space for dialogue, listening and information allows members of the public to access updated materials, ask questions, report any issues and gain a better understanding of the changes underway across the FERROVIENORD network. The Information Point is located in the entrance corridor on the right-hand side of the station and is open to the public Monday to Thursday, from 8:30 a.m. to 12:30 p.m.